Discover why insufficient cooling of these specialist rooms can have far-reaching consequences for a data centre – and how collaboration and smart design can avoid potential catastrophe.
On paper at least, a prefabricated containerised electrical room (CER) (or containerised electrical plantroom/Pods (CEP)) that houses the electrical infrastructure for a data centre – including switchgear, Uninterruptible Power Supply (UPS) and associated cooling systems – is an excellent solution from both a logistical and cost point of view. Often ‘shipping container’-sized for ease of transport, they can be ordered, delivered and installed with the same design used across multiple sites.
That almost sounds ‘plug and play’ – or as close as you can get with something as complex and sophisticated as a data centre. However, in reality, CERs can represent a serious risk to your business if not properly designed or installed. The issue? Overheating during commissioning due to airflow issues.
JDA’s Design and Commercial Manager, Robert Pidgeon, explains: “They overheat due to the airflow rate of the cooling unit being less that the air flow rate of the UPS – or a lack of containment of warm return air – which leads to air re-entrainment back into the UPS. There can also be a failure to accommodate heat gains from components including switchgear.”
Cause & effect
The fallout from an overheated CER can be significant: “The UPS will go into bypass,” explains Michal Piorkowski, JDA’s Intermediate Design Engineer. “This is where the Rectifier/Inverter module gets too hot and the unit switches back to mains power. However if there is no mains power, the power to the IT equipment is shut off. This has serious commercial implications as data centre operators are required to achieve a certain availability.”
As well as the significant financial impact associated with any potential downtime or drop in overall operational efficiency, there is also the cost of retrospectively fixing the design issue triggering the problem in the first place. Typically, solutions are charged at a premium because of the urgency of the solution.
High risk
Temporary quick fixes can be considered – but come with their own risks. For instance, polycarbonate sheets can be positioned above the UPS. “This blocks the warm air flow, preventing it from mixing and circulating back into the UPS,” says Piorkowski. “This is known as warm air containment.”
However, these sheets often require additional sprinklers to be installed in any new zones created. Existing fire alarms – chiefly smoke detectors – can also be affected as they will have been originally placed based on specific airflow patterns in the room before the incident. Disrupt these patterns with a polycarbonate sheet and you risk being left with the detection of fire or smoke either being delayed – or failing.
Smarter design
For all these potential downsides, CERs are by no means flawed – far from it. However, great care must be taken with the initial design of the room coupled with deep collaboration between stakeholders to ensure airflow requirements are fully assessed and met.
To help guide your CER implementation strategy, Pidgeon and Piorkowski offer the following advice for design and implementation success:
- Consider your CER’s design from the very start of your data centre planning and employ a design consultant to review the holistic design of your chosen container.
- Specific computational fluid dynamics of the deployed solution should be calculated and adequate time must be allowed during commissioning to test all real-world scenarios.
- Any changes made during the install period need to be checked for impacts on operation prior to commissioning to ensure it has been fully assessed.
- Consider the air-tightness of the CER as a whole and the containment itself; any supply air from the cooling unit should factor in any leakage out of the room. This will ensure there is a positive pressure at the inlet to the UPS.
As Pidgeon explains, “the overheating issue has popped up on a few different projects where there haven’t been proper cooling processes put in place and we’ve been brought in to resolve the issues.” However, JDA would prefer that you never experience the problem in the first place. It’s why we recommend talking with a specialist before the install to ensure your airflows, bottom line – and data centre – remain protected at all times.
Vet your CER plan
Talk to one of our specialists in an initial scoping meeting about your containerised electrical room requirements.