100% Renewable Energy Powered Data Centre

In theory, renewable energy can be used to power data centres. However, there are complexities and real-world challenges to overcome, particularly in the case of a 200MW facility. For this article, nuclear power will not be considered.

Available Technologies

In the UK, the main form of renewable energy is:

  • Solar
  • Wind – offshore and onshore
  • Bioenergy
  • Hydro
How many acres of land for PV would be required for a 200MW IT Data Centre Campus?

To clarify, this is assuming 100% solar power use to power a data centre and there will be no use of grid power.

Its key to factor in peak and annualised PUE. Therefore, you would need to assume an approximate 300MW peak demand requirement (1.5 peak PUE) and 240MW (1.2 annualised PUE).

Using the UK as the base case, it does not receive significant sunlight throughout the year, and a typical capacity factor value is 10%.

Using the assumptions, the approximated land needed for solar power to produce the 240MW is 16000 acres, in a southerly orientation. For context, the blue area below shows this approximately as a mass over London to outline the sheer scale of the PV array.

London is a big city, so Liverpool has also been used for additional context. As you can see, it essentially covers the entire area.

Then you have the logistical challenges. The quantity of solar panels required would be enormous – this would need between 10-20million panels (depending on the size).

There is the logistical challenge of installing this number of panels – it has never been done before. It would need to be phased over a large amount of time. Additionally, the power would need to be stored, typically in batteries, but this would need to be assessed. There would also be export challenges to consider amongst many other ecological and social problems that would be encountered.

Furthermore, lets also consider that a 200MW facility is not the largest facility or campus that are being discussed. There are campuses out there at present that are significantly higher than this number that would require multiples of this land capacity.

What about using wind power?

Wind power is an alternative. The London array, which has a rated capacity of 630MW via 175 turbines @ 40% capacity factor is used as the example in this case.

https://digital-library.theiet.org/doi/10.1049/etr.2014.0094

The London array’s annual production of power is not far away from the total power of our fictional 200MW data centre facility, and it provides some context from a wind farm perspective around how large this would need to be to produce the required power. However, its key to consider it cost 2.2b euros to build.

https://uk.rwe.com/

By no means is the London Array the largest wind farm in the UK, but it does show the scale required to produce the power alone.

Location

The majority of Data Centres are being built in urban areas, and this creates another challenge of where you could locate the renewable power close by that would directly feed the data centre facility. As the example above shows, the significant amount of land required for the power is simply not feasible. There is the argument the solar farm (or equivalent) could be ‘off-site’, but there is the additional challenge of then directly feeding in the power to the facility.

Impacts and Public Perception

Data centres are not always seen favourably, meaning there could be opposition to the planning of such a facility. However, solar farms and wind turbines often encounter similar opposition from varying perspectives, therefore you are potentially doubling the opposition potential if powering via a dedicated renewable energy source to the facility. Whilst renewable energy itself is favourable, the scale required for power production will inevitably only amplify opposition and project challenges.

It’s common to hear people assume everything can be powered via renewable energy sources without consideration for the scale required or complexities to overcome. This is something that will improve as technologies advance, but it will not go away.

Positives of Renewable Energy

Put simply, as a society, we must move away from those traditional forms of power production (natural gas, oil, coal etc). Positive steps are being taken and there is the constant expansion of solar and wind, in particular, all over the UK. This is evident throughout, whether you’re driving through Devon, or peering out to sea from East Anglia, there are examples everywhere. Each year, Renewable Energy is eating a larger chunk of the power pie as it grows and provides us with more of the power we use. But the argument is, is it large and consistent enough to power a mission critical asset. Probably not, but there is a place for it.

Realistic Snapshot and Conclusion

The purpose of this document was not to completely wipe out the idea of renewable energy to power data centres, but more to raise awareness of simply how much energy is required for the latest type of facilities and its impacts. Due to the sheer scale of renewable power required, a dedicated feed from a facilities own renewable energy source is not realistic from a technical, cost, or logistic perspective. However, there is always the potential to use renewable energy, but from the grid. Therefore, the argument is for growth in renewable energy, but from a grid perspective to ensure the incoming power is from renewable sources.